SRR3 & SRR4 RESULTS
Total Building Program (conventional as planned):
New Conventional Construction of two (2) Commercial/Lab Office Buildings, totaling 1.2Mil GSF, (624,000 SF/each) for a discreet cost model of $200M/each and 36 months/each in construction duration.
Total Program Cost: $400M, 72 months
TGE Top DownSM Program Performance Results (Actuals)
SRR3 Completion: 2017. 22 months total duration at a construction cost of $134 Million US
SRR4 Completion: 2018. 12 months total duration at a construction cost of $110 Million US
SRR3 & SRR4 certified LEED Platinum U.S. Green Building Council
$166 M SAVINGS OVERALL CONSTRUCTION COST SAVINGS
38 MONTH SCHEDULE SAVINGS 50% TIME SAVINGS
Reduced material weight, LEAN Building Design & Construction
Pre-assembled off-site construction efficiency improvements