Projects

SRR3 & SRR4 RESULTS

 

Total Building Program (conventional as planned)

 

New Conventional Construction of two (2) Commercial/Lab Office Buildings, totaling 1.2Mil GSF, (624,000 SF/each) for a discreet cost model of $200M/each and 36 months/each in construction duration. 

 

Total Program Cost: $400M, 72 months

TGE Top DownSM Program Performance Results (Actuals)

 

SRR3 Completion:  2017.  22 months total  duration at a construction cost of $134 Million US

 

SRR4 Completion:  2018.  12 months total duration at a construction cost of $110 Million US

SRR3 & SRR4 certified LEED Platinum U.S. Green Building Council

SRR3 Certification
SRR4 Certification in Application

$166 M SAVINGS OVERALL CONSTRUCTION COST SAVINGS


38 MONTH SCHEDULE SAVINGS 50% TIME SAVINGS


Reduced material weight, LEAN Building Design & Construction


Pre-assembled off-site construction efficiency improvements

TGE Technology 1